This really depends on the project. It it's ready to tile when I walk in, then 5 days. That would include mortar shower pan, complete water proofing, building a niche, tile and grout.
If the project has an acrylic or similar shower pan, then subtract a day, if tear out and re-sheating are required, then add one to two days.
People work at different speeds, but people also charge different rates, so doing a fair comparison is not always easy.